| Serpentine Hot Springs Access Road ADOT&PF Project No. 62205 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Printable version of Serpentine Hot Springs Access Road scoping letter | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| The Alaska Department of Transportation and Public Facilities (DOT&PF), in cooperation with the Federal Highways Administration (FHWA) is proposing improvements to Serpentine Hot Springs Access Road (also known as the Taylor Highway). Serpentine Hot Springs Access Road is an extension of the Nome-Taylor Highway which originates in Nome, Alaska. The project area includes a 18 mile stretch from mile post (MP) 68 to MP 85.5, and three material source locations adjacent to the road (1:63360 USGS Quadrangles Bendeleben A-6 and B-6) (Figure 1). | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Existing
Condition/Purpose and Need The Serpentine Access Road was established approximately 60 years ago by the Alaska Road Commission (ARC). It serves as the only access to the Serpentine Hot Springs trailhead, and current average daily traffic is less than 50 vehicles per day. The existing road is approximately 24 feet wide, and in some areas, the adjacent vegetation has become overgrown, hindering driver sight distance. Sections of the road suffer annual seasonal flooding, due to permafrost melt. The lack of drainage ditches, combined with permafrost melt and water ponding alongside the road has caused erosion of the roadbed and occasionally renders the road impassible. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Proposed
Action Improvements would be made to the road along approximately 26 short segments that total approximately 2-1/2 miles of the overall 18-mile project corridor. The location of these areas is shown on Figure 2 and proposed work for each segment is summarized in the table below. Proposed improvements include restoration of road embankments, installation of culverts, filling of ponded areas adjacent to the road, construction of drainage ditches, and brush cutting to increase sight distance. In areas where ditches need to be cut and slopes laid back, the fill footprint would be approximately 20-25 feet beyond the existing road shoulder. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Three material sources, located adjacent to the road, are being considered for the project, as shown on Figure 2. The proposed improvements would occur within the existing 200-foot right-of-way (ROW) (Figure 2). Construction may begin as early as Summer 2008. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Preliminary Research
Results An agency scoping meeting and/or site visit can be arranged, upon request. Scoping comments can be submitted by mail or e-mail to the address listed below. To ensure that all factors are considered in the environmental and design studies, your comments are requested by October 12, 2007. Below is a list of federal, state and local entities that we are requesting input from. Please click on the organization that you represent. This will take you to a list of questions specific to your purview, as well as a "comments" link that can be used to submit comments electronically. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Comment letters can also be sent to our Environmental Consultant, Kristen Hansen, at DOWL Engineers, at 4041 B Street, Anchorage, Alaska, 99503. Ms. Hansen may be reached by telephone at (907) 562-2000, or e-mail to khansen@dowl.com. Should you have any questions on the design of the proposed project, contact Cindie Little, P.E., Design Engineering Manager, at (907) 451-2284 or send e-mail to cindie.little @alaska.gov. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||